I-5 Rose Quarter Improvement Project Completed Ahead of Schedule
PORTLAND, Ore. (KATU) — The Oregon Department of Transportation (ODOT) has announced the early completion of the I-5 Rose Quarter Improvement Project. This significant infrastructure project wrapped up more than a week ahead of its planned timeline.
Project Overview
Initially scheduled to last five weeks, the project commenced on September 11, with an expected completion by October 16. The primary focus was on addressing and reinforcing weak points along the southbound lanes of I-5 within the Rose Quarter area of Portland.
Key Improvements
- Repair and reinforcement of deficient sections along southbound I-5.
- Replacement of bridge joints to enhance structural integrity.
- Repaving of the interstate surface for improved driving conditions.
- Removal of the concrete surface layer south of the Moda Center, allowing for crucial base layer repairs and resurfacing.
Reopening Timeline
ODOT officials confirmed that crews will begin re-striping the southbound lanes starting Wednesday night. The full reopening of I-5 is projected to occur approximately 24 hours after work begins, with traffic expected to resume by 10 p.m. Wednesday.